Mesaba Energy Project Print Page

Mesaba Energy Project Schedule

Significant Milestones Achieved to Date
  • Enabling Legislation (View) enacted by Minnesota Legislature in June 2003
  • Secured Development Funding including:
    • $36 million from the U.S. Department of Energy
    • $9.5 million from Iron Range Resources
    • $10 million grant from the Renewable Development Fund
  • Energy Policy Act of 2005 provides for Federal loan guarantees for the Project and provides a pool of investment tax credits for a handful of IGCC projects
  • Filed petition for approval of power purchase agreement with Minnesota Public Utilities Commission on December 27, 2005; case pending before an administrative law judge
  • Project engineering, procurement and construction (EPC) consortium (Fluor, ConocoPhillips and Siemens) completed optimization and initial pricing engineering studies
  • Application for all material pre-construction permits has been filed with the Minnesota Public Utilities Commission and deemed complete by the PUC
  • Federal environmental information volume completed as part of environmental impact statement process conducted by U.S. Department of Energy
  • Granherne, a business unit of KBR Engineering, serves as owner's engineer
  • The Project is being designed to be fuel flexible, to take advantage of the best fuel prices over the life of the plant
  • Acquired an option to purchase the West Range site
  • Large Generator Interconnection Request has been submitted
  • Transmission System Impact Studies are under way
Significant Milestones To Be Achieved
  • Execution of large generator interconnect agreement (LGIA)
  • Issuance of pre-construction permits
  • Minnesota PUC approval of the power purchase agreement
  • Completion of front end engineering and design by Fluor, Siemens and ConocoPhillips
  • Execution of engineering, procurement, and construction contract
  • Financial close
  • Final design
  • Construction
  • U.S. Department of Energy demonstration period and start of operations