Mesaba Energy Project Schedule

Significant Milestones Achieved to Date
- Enabling Legislation (View)
enacted by Minnesota Legislature in June 2003
- Secured Development Funding including:
- $36 million from the U.S. Department of Energy
- $9.5 million from Iron Range Resources
- $10 million grant from the Renewable Development Fund
- Energy Policy Act of 2005 provides for Federal loan guarantees for the
Project and provides a pool of investment tax credits for a handful of IGCC
projects
- Filed petition for approval of power purchase agreement with Minnesota
Public Utilities Commission on December 27, 2005; case pending before an
administrative law judge
- Project engineering, procurement and construction (EPC) consortium (Fluor,
ConocoPhillips and Siemens) completed optimization and initial pricing
engineering studies
- Application for all material pre-construction permits has been filed with the Minnesota Public Utilities Commission and deemed complete by the PUC
- Federal environmental information volume completed as part of environmental
impact statement process conducted by U.S. Department of Energy
- Granherne, a business unit of KBR Engineering, serves as owner's engineer
- The Project is being designed to be fuel flexible, to take advantage of the
best fuel prices over the life of the plant
- Acquired an option to purchase the West Range site
- Large Generator Interconnection Request has been submitted
- Transmission System Impact Studies are under way
Significant Milestones To Be Achieved
- Execution of large generator interconnect agreement (LGIA)
- Issuance of pre-construction permits
- Minnesota PUC approval of the power purchase agreement
- Completion of front end engineering and design by Fluor, Siemens and
ConocoPhillips
- Execution of engineering, procurement, and construction contract
- Financial close
- Final design
- Construction
- U.S. Department of Energy demonstration period and start of operations
|